← Field Notes

Regulation and Records

The 2019 gas transmission rule and what spike testing changed

If your pressure testing procedure predates 2019 and has never been revised, it is missing something.

What was added

The 2019 gas transmission rule added 49 CFR 192.506, the spike hydrostatic pressure test, to the requirements for gas transmission pipelines.

A spike is a short excursion to a pressure above the strength test pressure, held briefly at the start of the test sequence.

What a spike is for

Conventional strength holds are good at finding defects that cannot carry the load. They are less good at finding time-dependent features — stress corrosion cracking, certain seam anomalies — that survive the hold and then grow in service.

A brief excursion to a higher pressure is intended to fail those features during the test, when the line is full of water and a crew is present, rather than later.

Sequence matters

The spike comes first, before the strength and leak holds. This is not arbitrary: applying a higher pressure after a long hold does not achieve the same thing, and a procedure that places it at the end has misunderstood the mechanism.

Check your procedureThe sequence should be explicit: spike, then strength, then leak, with the pressures and durations for each and the acceptance criteria against each.

What it does to planning

The spike pressure raises the maximum pressure any component in the segment will see, which flows back into every rating check.

  • Temporary works — heads, manifolds, hoses — must be rated above the spike, not above the strength pressure
  • The low point of the segment sees spike pressure plus static head
  • Elevation windows may narrow, because the ceiling moved
  • Fittings previously acceptable at strength pressure need re-checking

Records

The spike is part of the test and belongs in the record with its own pressure, duration and acceptance, retained for the life of the pipeline under 192.517.

Verify all of this against the current text of the CFR before applying it. This is orientation, not the regulation.

Standing noteThis is educational reference material, not engineering advice. Regulations are revised continually; the editions in force at the time of a project govern, and every project requires its own qualified engineering analysis and the operator’s governing specifications.

From Proper Pigging, the hydrostatic and nitrogen test field book, and the HydroTech certification courses built on it.