Regulation and Records
The 2019 gas transmission rule and what spike testing changed
If your pressure testing procedure predates 2019 and has never been revised, it is missing something.
What was added
The 2019 gas transmission rule added 49 CFR 192.506, the spike hydrostatic pressure test, to the requirements for gas transmission pipelines.
A spike is a short excursion to a pressure above the strength test pressure, held briefly at the start of the test sequence.
What a spike is for
Conventional strength holds are good at finding defects that cannot carry the load. They are less good at finding time-dependent features — stress corrosion cracking, certain seam anomalies — that survive the hold and then grow in service.
A brief excursion to a higher pressure is intended to fail those features during the test, when the line is full of water and a crew is present, rather than later.
Sequence matters
The spike comes first, before the strength and leak holds. This is not arbitrary: applying a higher pressure after a long hold does not achieve the same thing, and a procedure that places it at the end has misunderstood the mechanism.
What it does to planning
The spike pressure raises the maximum pressure any component in the segment will see, which flows back into every rating check.
- Temporary works — heads, manifolds, hoses — must be rated above the spike, not above the strength pressure
- The low point of the segment sees spike pressure plus static head
- Elevation windows may narrow, because the ceiling moved
- Fittings previously acceptable at strength pressure need re-checking
Records
The spike is part of the test and belongs in the record with its own pressure, duration and acceptance, retained for the life of the pipeline under 192.517.
Verify all of this against the current text of the CFR before applying it. This is orientation, not the regulation.