How to evaluate a pipeline pressure testing contractor
Most of what distinguishes a good pressure testing contractor is visible before award, in the answers to questions that cost nothing to ask.
Ask for the analysis method, not the price
The question that separates contractors fastest: how will you predict the pressure–temperature response for this segment, and what will you measure to do it?
A contractor who can answer with the relation, the coefficients and the instrumentation plan has done this properly before. One who says the crew will watch the gauge has not.
Instrumentation and resolution
- What pressure instrument, and what resolution?
- How many temperature points, where, and how weighted?
- Deadweight tester as the site pressure standard, and when was it last certified?
- Chart recorders, loggers, and what redundancy?
Every instrument needs a calibration certificate whose serial number matches the equipment on site. Ask to see one before award, not on the day.
Acceptance criteria before mobilisation
A contractor who wants the acceptance criteria agreed in writing before mobilising is protecting both of you. One who is relaxed about settling it later is planning to negotiate from a position of having already spent your money.
The temporary works
Test heads, manifolds and hoses see full test pressure and are the components most often taken on trust. Ask for ratings and proof-test records for the temporary works specifically.
This is where the serious injuries in this work come from.
Records
49 CFR 192.517 and 195.310 require test records to be retained for the life of the pipeline. Ask what you will receive, in what format, and when.
A contractor whose deliverable is a signed one-page summary has not understood the obligation you are under.
The honest tell
Ask what a pressure test cannot prove. A contractor who answers well — short holds can miss very slow leaks, the test proves a margin at a moment, pressure reversals are possible on bleed-down — is someone who will tell you the truth when a result is ambiguous.
A contractor who sells certainty will sell you certainty again when the trace is unclear, and that is precisely when you need the other kind.