Pigging Operations

Pig tracking and signallers, and what to do when a pig goes quiet

A pig that has not been confirmed at the receiver is not necessarily stuck. Treating those two states as identical is how crews turn a delay into an incident.

Confirming passage

Passage is confirmed by signallers at the traps and, on longer or more critical runs, at intermediate points. A signaller is a mechanical or magnetic device tripped by the pig as it passes.

Independent of the signallers, the flow behaviour tells you something: differential pressure across the run rises as a pig works and settles when it arrives.

A missed signal is not a stuck pig

Signallers fail, are not reset, or are read by someone who was not watching. Before concluding that a pig is stuck, confirm the instrument.

The cost of the two errors is asymmetric. Assuming a pig is stuck when it is not costs time. Assuming a pig has passed when it has not can put a crew in front of a trap closure with a pig and an inventory behind it.

When it really is stuck

The sequence is: stop, do not increase drive pressure indefinitely, and locate before acting.

Increasing pressure to free a pig is the instinctive response and the one that most often makes the situation worse, because a pig that suddenly frees under high differential accelerates.

  • Confirm launch and confirm non-arrival independently
  • Review the differential pressure record for where it changed
  • Use tracking equipment to locate, working from the last confirmed position
  • Plan the recovery, including what happens to the inventory behind the pig

Designing runs so this is less likely

Most stuck pigs are explained by something known in advance: an unbarred tee, a reduced-bore valve, an unrecorded diameter change, or a pig chosen without reference to the worst geometry in the run.

The line list and the drawings are the prevention. Reviewing them is cheaper than a recovery.